In Fort Mcmurray, Alberta, APM Canada mobilized at Heartland Muskeg River for a hot gas path inspection. The outage lasted from March 27, 2024 until April 15th, 2024 and ended with approximately 4,000 manhours completed with ZERO recordable injuries or quality issues! The team’s dedication to the Live Outage initiative impressed the customer and aided their success.
Read MoreAPM Canada mobilized a small crew for setup on October 19th, 2022 and officially started the TransAlta Sarnia outage on October 28th until demobilization on November 30th. The job scope included an Alton 11N2-C Inspection with Gen Bearing Inspections. Even with a grand total of 7,627 manhours, APM Canada completed the job ahead of schedule with zero safety or quality incidents!
Read MoreMobilized in late July, the skilled APM Canada team independently reported to a fertilizer plant in Redwater, Alberta, to complete a large-scale project within a tight timeline of roughly two months. The rounded project scope included replacing a Westinghouse turbine unit, the turbine’s auxiliary equipment, two ID fans, gear boxes, the turbine’s frame, and vetting equipment start up before entering full repower.
Read MoreWhile on site to provide a 7FA major inspection, exhaust upgrade, and a generator swap for Thorold Cogeneration Station at Northland Power in Ontario Canada, APM Canada participated in an exciting joint activity to raise funds for charity along with keeping all craft and site workers engaged in Toolbox Talks and safety discussions. The first activity incentivized continual safety, and site teams contributed to a fund pot each day of the outage. The opportunity to give back to the local community sparked high participation amongst crews.
Read MoreAPM Canada completed an installation for our new customer in July 2020. Their commitment to providing a safe outage with quality excellence at the forefront brought shining recognition from our customer.
Read MoreWe are extremely proud of our APM Specialty Services Canada team and their contribution to the success of the Saddle West Expansion project. In collaboration with Baker Hughes, APM brought the culture of teamwork and a strong performance of safety to TC Energy in Alberta, Canada. All contractors participating in the project held a high sense of accountability. This drew recognition in being selected for the CEO Safety Leadership Awards in 2019 under the team category for their inspiring sense of mutual success, and powerful performance in safety.
Read MoreTypically, APM, FieldCore, and GE meet in person to set out a pre-planning process for an outage. Due to the current environment within COVID-19, multiple calls were made with APM Canada Director – Ben Jonas, Service Managers – Craig Mosier and Ben Storie, Lead EHS Representative – Rob Dunbar, and Superintendents – Derek Steele and Jeremy Johnson to discuss optimal work completion at Husky Energy in Lloydminster, Saskatchewan.
Read MoreAPM Canada recently achieved a major accomplishment at the Syncrude Power Plant near Fort McMurray, Alberta, Canada. The team attained the incredible when they completed one hundred shifts, incident free...