APM Steam Services U.S. successfully completed two outages in sequence and ahead of schedule during the 2020 Spring outage season. Both projects were critical components within a total of five LP steam path replacements listed for the customer.

Powered by teamwork

Duke+Nuclear+1.jpg

The 114-strong Steam Services teams consisted of APM Millwrights, Operating Engineers and Superintendents. These teams racked in over 100,000 manhours during both outages combined. Day and night shift Superintendents from the Oconee team, Terry Jennings, Jonathan Davis, James Jennings, Earl Smith, Chris Pace, Juan Ramirez; and the Catawba team, Greg Gibbs, Stephen Kotter, Kevin Gray, Anthony “Ace” Reed, Michael Wells, and Adam Ringling, delegated their leadership to ensure achievement of key project goals.

Integration of all supportive teams on site delivered productivity initiatives such as, optimized steam seal piping modifications to eliminate numerous critical path welds, and joint mounted gantry cranes which allowed four cranes to operate simultaneously.

Significant corrective design and service actions put in place during Fall 2019 continue to run well with no repeated adjustments needed.

Duke+Nuclear+2.jpg

Safety Strengths

The use of diaphragm storage racks and bearing tables to minimize part movement contributed to an increased level of safety for all functioning teams at the site. Our APM crews did an awesome job in following protocols to remain safe and healthy.

Customer Fulfillment

As part of the One GE Field Service Solution, our customer complimented on craft execution, leadership, and emphasized how our crews tackle difficult tasks with expertise and ease.

Collaboration on complex scopes drove significant improvements that allowed both outages to end two days ahead of schedule and help our customer return to full power.

Thank you to our Steam Services site team, for continuing to establish APM excellence in safety and quality during outages for our customers!